Construction Industry Forums
Directory Listings
Top Navigation Bar
Construction
Top Navigation Bar Construction Directory Construction Exchange Links Link to Us Link to Us Free Services Free Services Advertise Advertise Site Info Site Info Site Map Site Map Search our Web Site Search our Web Site Contact Us Contact Us Privacy Privacy Top Navigation Bar
Top Navigation Bar Press Releases Press Releases Construction Industry Articles Construction Industry Articles Construction Trends Construction Trends Submit Construction Articles Submit Construction Articles Webfeed Generator Webfeed Generator Webfeed Generator Webfeed Generator Webfeed Generator Webfeed Generator Tell a Friend Tell a Friend Forums
Forums
Construction Industry

Google Custom Search
  Construction Industry Forum
  Home Planning Tips
  Layout of Building

Post New Topic  Post A Reply
profile | register | preferences | faq | search

UBBFriend: Email This Page to Someone! next newest topic | next oldest topic
Author Topic:   Layout of Building
Neha Gupta
New Member

Posts: 1
From: Sonepat, Haryana, India
Registered: Aug 2008

posted August 14, 2008 01:38 AM     Click Here to See the Profile for Neha Gupta     Edit/Delete Message   Reply w/Quote
Layout of Building

Layout

The real meaning and purpose of setting out (layout) is to transfer the plan, length and width of its foundation on the ground so that the foundation can be excavated for construction of purposed building as per drawing.

The following preliminary works should be executed before actual planning of layout for the house.

* Clear the site from all grass, bushes, trees, etc.
* Record spot levels of the ground.
* Construct a permanent bench mark in construction area.

Base Line

For setting out /layout, the most important requirement is to establish a baseline. This is marked on the ground as per site plan requirement with the help of offsets which are taken from the existing road or existing building.

Centre Line

Centre line divides the plan into two equal parts. This can be marked in the field with the help of baseline. This line is very necessary and useful for layout. This line should be transferred to Burjis and be kept up to the completion of foundation work.

'Burjis' and its' Distance

Burji or marking pillars are masonry pillars constructed with bricks and cement mortar. These are constructed on both ends of walls /columns and center line should be marked on the top surface of the burjis with the help of base line. Burji is also constructed for indicating the plinth level of the building. Burjis are very useful for the layout. Accuracy of the foundation can be checked with the help of Burji at any time during construction. Burjis should be kept intact till completion of foundation work.

http://www.gharexpert.com/

------------------
Nenni

IP: Logged

All times are PT(US)

next newest topic | next oldest topic

Administrative Options: Close Topic | Archive/Move | Delete Topic
Post New Topic  Post A Reply
Hop to:

Contact Us | Great Possibilities.com | Privacy Statement

Powered by Infopop www.infopop.com © 2000
Ultimate Bulletin Board 5.47d

Construction Industry
© 2008 Great Possibilities, Inc. All rights reserved.